Things are coming together,
From Jim Hall, our contractor:
We finished the upper deck, framed the walls at the second floor entry overlook and fireplace at ceiling, installed SGD hardware and interior door handles. Eric will finish tile Tuesday while we put the sub tops on the laundry and desk counters. Wed the laminate counter go on and the drywall work will be done. Thursday we run baseboard downstairs and do a major cleanup. Friday the kitchen and vanity tops go in. Monday the back splash gets started. Tuesday and Wednesday the bamboo floor and stairs go down.
We'll post pictures this weekend!
As our niece Sophie used to say, "I'm happy now!"
No comments:
Post a Comment